First phase of critical East Molokai upgrades completed
Hawaiian Electric hardened power lines and poles to reduce wildfire risk
Release Date: 10/21/2026
KAHULUI, Oct. 21, 2026 – Hawaiian Electric has completed the first phase of a major grid hardening project along East Kamehameha V Highway in East Molokai, successfully upgrading more than 8 miles of power lines and 27 utility poles to improve reliability and reduce wildfire risk for the community.
The project focused on a section of East Kamehameha V Highway between Onioni Drive and Ualapue, an area identified as a priority for grid hardening based on wildfire risk factors. The upgrades included replacing existing copper power lines with new aluminum conductors and strengthening critical infrastructure along the corridor.
Plans prioritized safety, customer impact
Since crews cannot safely perform this work on energized copper lines, planned daytime outages were required to complete the project. Hawaiian Electric took several steps to reduce impacts and support customers throughout the work:
- Brought in 26 additional crewmembers, five employees, nine vehicles and two generators from Maui, Hawaii Island, and Oahu, reducing what could have been a month-long project to six days.
- Scheduled the work during fall break to avoid disruptions at Kilohana Elementary School.
- Conducted outreach three weeks in advance through mailed notices, phone calls, emails and a virtual community meeting after the project schedule was finalized following storm restoration efforts on neighboring islands.
- Established a customer hub at the only store on the East End, Manae Goods & Grindz, providing device charging, internet access, project updates and ice vouchers for affected customers.
- Hosted an in-person community meeting at Kilohana Elementary School during the project to provide updates and hear feedback before continuing with the planned outages.
Minimizing customer impact, supporting our community
As a result of the crews' efficiency and hard work, Hawaiian Electric eliminated the need for outages on two of the originally scheduled outage days, reducing customer impacts from six days to four and restoring normal service sooner than anticipated.
The customer hub welcomed approximately 150 customers total and provided approximately 700 bags of ice. Customers had an opportunity to ask questions, learn more about the project and see firsthand the differences between the existing copper wire and new aluminum conductors.
On the second day of the project, Hawaiian Electric hosted an in-person community meeting to provide a status update and give customers an opportunity to share feedback as the work continued throughout the week. The handful of customers in attendance expressed appreciation for the effort to complete the project within that week and for the support provided throughout the outages.
Mahalo to the East Molokai community for its patience, flexibility and kokua throughout the project. Hawaiian Electric is planning for a second phase of grid hardening improvements that includes the replacement of over 100 poles on the East End of Molokai in 2027 and 2028, pending various permitting approvals.