Selling Power to the Utility

Share

Stage 3 Oahu RFP Schedule

Schedule as of 9/27/2023

Milestone Schedule Dates
(1) Draft RFP filed May 2, 2022
(2) Community Meeting May 24, 2022
(3) Parties and Participants file Comments by June 2, 2022
(4) Community Meeting 2 July 14, 2022
(5) Technical Status Conference August 5, 2022
(6) Order 38735 Issued December 1, 2022
(7) Proposed Final RFP Filed December 22, 2022
(8) Final RFP issued by January 20, 2023
(9) Hawaiian Electric and Affiliate Proposal Due Date April 19, 2023 at 2:00 pm HST
(10) IPP Proposal Due Date April 20, 2023 at 2:00 pm HST
(11) Selection of Priority List July 6, 2023
(12) Hawaiian Electric and Affiliate BAFOs Due July 13, 2023
(13) IPP BAFOs Due July 14, 2023
(14) Selection of Final Award Group December 1, 2023
(15) IRS and Contract Negotiations Begin December 8, 2023