Selling Power to the Utility

Stage 3 Hawaii RFP Schedule

Proposed Schedule as of November 7, 2022

Milestone Schedule Dates
(1) Draft RFP filed October 15, 2021
(2) Community Meeting October 28, 2021
(3) PUC Review and Further Direction January 20, 2022
(4) Company filed 2nd Draft March 18, 2022
(5) Technical Conference April 14, 2022
(6) Company filed 3rd Draft May 31, 2022
(7) Order 38653 October 17, 2022
(8) Proposed Final RFP filed November 7, 2022
(9) RFP is Issued November 21, 2022
(10) Hawaiian Electric and Affiliate Proposal Due Date February 23, 2023 at 2:00 pm HST
(11) IPP Proposal Due Date February 24, 2023 at 2:00 pm HST
(12) Selection of Priority List May 10, 2023
(13) Hawaiian Electric and Affiliate BAFO Due Date May 17, 2023
(14) IPP BAFO Due Date May 18, 2023
(15) Selection of Final Award Group August 31, 2023
(16) Contract Negotiations Start September 7, 2023