Proposed Schedule as of August 31, 2021

Milestone Schedule Dates
(1) Draft RFP filed July 9, 2020
(2) Technical Status Conference July 29, 2020
(3) Parties and Participants file Comments by August 12, 2020
(4) Proposed Final RFP filed September 8, 2020
(5) Updated RFP Draft filed Per Order 37592 March 30, 2021
(6) Parties and Participants file Comments by April 14, 2021
(7) Proposed Updated RFP filed August 31, 2021
(8) Final RFP is Issued September 22, 2021
(9) Self-Build Proposal Due Date November 22, 2021 at 2:00 pm HST
(10) IPP and Affiliate Proposal Due Date November 23, 2021 at 2:00 pm HST
(11) Selection of Priority List February 1, 2022
(12) BAFOs due February 8, 2022
(13) Selection of Final Award Group May 24, 2022
(13) Contract Execution Start May 31, 2022