Selling Power to the Utility
IGP RFP Schedule
Schedule as of 8/28/2026
| Milestone | Schedule Dates |
|---|---|
| (1) Community Meeting | March 11, 2024 |
| (2) Developer Meeting | March 20, 2024 |
| (3) Draft RFP Filing Date | April 30, 2024 |
| (4) Comments for 4/30/2024 Draft RFP Due Date | May 30, 2024 |
| (5) Docket No. 2024-0258 Opened | August 19, 2024 |
| (6) Docket No. 2024-0258 Draft RFP Filing Date | August 26, 2024 |
| (7) Comments for 8/26/2024 Draft RFP Due Date | September 16, 2024 |
| (8) Draft RFP Filing in response to CA-IR-5 | March 12, 2025 |
| (9) Company’s complete response to Order No. 41594 | April 3, 2025 |
| (10) Parties SOPs | April 17, 2025 |
| (11) Company's Reply SOP | May 2, 2025 |
| (12) Parties’ SSOPs | August 8, 2025 |
| (13) Companies’ Reply SSOP | August 25, 2025 |
| (14) Order to Issue Final RFP | June 17, 2026 |
| (15) Issue RFP | August 7, 2026 |
| (16) Technical Conference | August 31, 2026 |
| (17) PIR Request Due Date | [5 weeks after RFP issuance] September 11, 2026 |
| (18) PIR Meetings Held | [13 - 16 weeks after RFP issuance] November 6, 2026 – November 27, 2026 |
| (19) Hawaiian Electric and Affiliate Proposal Due Date | [1 day before IPP Proposal Due Date] January 21, 2027 at 2:00 pm HST |
| (20) IPP Proposal Due Date | [24 weeks after RFP issuance] January 22, 2027 at 2:00 pm HST |
| (21) Selection of Priority List | May 20, 2027 |
| (22) Hawaiian Electric and Affiliate BAFOs Due | May 27, 2027 |
| (23) IPP BAFOs Due | May 28, 2027 |
| (24) Selection of Final Award Group | September 10, 2027 |
| (25) IRS and Contract Negotiations Begin | September 24, 2027 |