Schedule as of 8/26/2024

Milestone Schedule Dates
(1) Community Meeting March 11, 2024
(2) Developer Meeting March 20, 2024
(3) Draft RFP Filing Date April 30, 2024
(4) Comments for 4/30/2024 Draft RFP Due Date May 30, 2024
(5) Docket 2024-0258 Opened August 19, 2024
(6) Docket 2024-0258 Draft RFP Filing Date August 26, 2024
(7) Comments for 8/26/2024 Draft RFP Due Date September 16, 2024
(8) Technical Conference October 2024
(9) Order to Issue Final RFP November 15, 20241
(10) Issue RFP November 19, 2024
(11) Preliminary Interconnection Report & Pre-Bid Meeting Request Due Date [3 weeks after RFP issuance]
(12) Pre-Bid Meetings Held [11-14 weeks after RFP issuance]
[February 4-25, 2025]
(13) Hawaiian Electric and Affiliate Proposal Due Date [22 weeks - 1 day after RFP issuance]
April 21, 2025 at 2:00 pm HST
(14) IPP Proposal Due Date [22 weeks after RFP issuance]
April 22, 2025 at 2:00 pm HST
(15) Selection of Priority List July 7, 2025
(16) Hawaiian Electric and Affiliate BAFOs Due July 14, 2025
(17) IPP BAFOs Due July 15, 2025
(18) Selection of Final Award Group October 27, 2025
(19) IRS and Contract Negotiations Begin November 3, 2025