IGP RFP Schedule

Schedule as of 8/28/2026

Milestone Schedule Dates
(1) Community Meeting March 11, 2024
(2) Developer Meeting March 20, 2024
(3) Draft RFP Filing Date April 30, 2024
(4) Comments for 4/30/2024 Draft RFP Due Date May 30, 2024
(5) Docket No. 2024-0258 Opened August 19, 2024
(6) Docket No. 2024-0258 Draft RFP Filing Date August 26, 2024
(7) Comments for 8/26/2024 Draft RFP Due Date September 16, 2024
(8) Draft RFP Filing in response to CA-IR-5 March 12, 2025
(9) Company’s complete response to Order No. 41594 April 3, 2025
(10) Parties SOPs April 17, 2025
(11) Company's Reply SOP May 2, 2025
(12) Parties’ SSOPs August 8, 2025
(13) Companies’ Reply SSOP August 25, 2025
(14) Order to Issue Final RFP June 17, 2026
(15) Issue RFP August 7, 2026
(16) Technical Conference August 31, 2026
(17) PIR Request Due Date [5 weeks after RFP issuance]
September 11, 2026
(18) PIR Meetings Held [13 - 16 weeks after RFP issuance]
November 6, 2026 – November 27, 2026
(19) Hawaiian Electric and Affiliate Proposal Due Date [1 day before IPP Proposal Due Date]
January 21, 2027 at 2:00 pm HST
(20) IPP Proposal Due Date [24 weeks after RFP issuance]
January 22, 2027 at 2:00 pm HST
(21) Selection of Priority List May 20, 2027
(22) Hawaiian Electric and Affiliate BAFOs Due May 27, 2027
(23) IPP BAFOs Due May 28, 2027
(24) Selection of Final Award Group September 10, 2027
(25) IRS and Contract Negotiations Begin September 24, 2027