IGP RFP Schedule

Schedule as of 5/2/2025

Milestone Schedule Dates
(1) Community Meeting March 11, 2024
(2) Developer Meeting March 20, 2024
(3) Draft RFP Filing Date April 30, 2024
(4) Comments for 4/30/2024 Draft RFP Due Date May 30, 2024
(5) Docket 2024-0258 Opened August 19, 2024
(6) Docket 2024-0258 Draft RFP Filing Date August 26, 2024
(7) Comments for 8/26/2024 Draft RFP Due Date September 16, 2024
(8) Draft RFI Filing in response to CA-IR-5 March 12. 2025
(9) Company's complete response to Order No. 41594 April 3, 2025
(10) Parties SOPs April 17, 2025
(11) Company's Reply SOP May 2, 2025
(12) Order to Issue Final RFP To Be Determined (TBD)1
(13) Issue RFP TBD
(14) Technical Conference TBD
(15) PIR Request Due Date [5 weeks after RFP issuance]
(16) PIR Meetings Held [13-16 weeks after RFP issuance]
(17) Hawaiian Electric and Affiliate Proposal Due Date [24 weeks - 1 day after RFP issuance]
TBD at 2:00 pm HST
(18) IPP Proposal Due Date [24 weeks after RFP issuance]
TBD at 2:00 pm HST
(19) Selection of Priority List TBD
(20) Hawaiian Electric and Affiliate BAFOs Due TBD
(21) IPP BAFOs Due TBD
(22) Selection of Final Award Group TBD
(23) IRS and Contract Negotiations Begin TBD

1This date and all subsequent dates in the final schedule are dependent on future guidance to be set by the PUC