Schedule as of 6/27/2025
| Milestone | Schedule Dates |
|---|---|
| (1) Community Meeting | March 11, 2024 |
| (2) Developer Meeting | March 20, 2024 |
| (3) Draft RFP Filing Date | April 30, 2024 |
| (4) Comments for 4/30/2024 Draft RFP Due Date | May 30, 2024 |
| (5) Docket 2024-0258 Opened | August 19, 2024 |
| (6) Docket 2024-0258 Draft RFP Filing Date | August 26, 2024 |
| (7) Comments for 8/26/2024 Draft RFP Due Date | September 16, 2024 |
| (8) Draft RFI Filing in response to CA-IR-5 | March 12. 2025 |
| (9) Company's complete response to Order No. 41594 | April 3, 2025 |
| (10) Parties SOPs | April 17, 2025 |
| (11) Company's Reply SOP | May 2, 2025 |
| (12) Order to Issue Final RFP | To Be Determined (TBD)1 |
| (13) Issue RFP | TBD |
| (14) Technical Conference | TBD |
| (15) PIR Request Due Date | [5 weeks after RFP issuance] |
| (16) PIR Meetings Held | [13-16 weeks after RFP issuance] |
| (17) Hawaiian Electric and Affiliate Proposal Due Date | [24 weeks - 1 day after RFP issuance] TBD at 2:00 pm HST |
| (18) IPP Proposal Due Date | [24 weeks after RFP issuance] TBD at 2:00 pm HST |
| (19) Selection of Priority List | TBD |
| (20) Hawaiian Electric and Affiliate BAFOs Due | TBD |
| (21) IPP BAFOs Due | TBD |
| (22) Selection of Final Award Group | TBD |
| (23) IRS and Contract Negotiations Begin | TBD |