IGP RFP Schedule
Schedule as of 8/26/2024
Milestone | Schedule Dates |
---|---|
(1) Community Meeting | March 11, 2024 |
(2) Developer Meeting | March 20, 2024 |
(3) Draft RFP Filing Date | April 30, 2024 |
(4) Comments for 4/30/2024 Draft RFP Due Date | May 30, 2024 |
(5) Docket 2024-0258 Opened | August 19, 2024 |
(6) Docket 2024-0258 Draft RFP Filing Date | August 26, 2024 |
(7) Comments for 8/26/2024 Draft RFP Due Date | September 16, 2024 |
(8) Technical Conference | October 2024 |
(9) Order to Issue Final RFP | November 15, 20241 |
(10) Issue RFP | November 19, 2024 |
(11) Preliminary Interconnection Report & Pre-Bid Meeting Request Due Date | [3 weeks after RFP issuance] |
(12) Pre-Bid Meetings Held | [11-14 weeks after RFP issuance] [February 4-25, 2025] |
(13) Hawaiian Electric and Affiliate Proposal Due Date | [22 weeks - 1 day after RFP issuance] April 21, 2025 at 2:00 pm HST |
(14) IPP Proposal Due Date | [22 weeks after RFP issuance] April 22, 2025 at 2:00 pm HST |
(15) Selection of Priority List | July 7, 2025 |
(16) Hawaiian Electric and Affiliate BAFOs Due | July 14, 2025 |
(17) IPP BAFOs Due | July 15, 2025 |
(18) Selection of Final Award Group | October 27, 2025 |
(19) IRS and Contract Negotiations Begin | November 3, 2025 |
1This date and all subsequent dates in the proposed final schedule are dependent on any further guidance to be set by the PUC