Selling Power to the Utility
Grid Services Maui RFP 4 Schedule
Proposed Schedule as of February 1, 2023
| Milestone | Schedule Dates |
|---|---|
| (1) RFP issued | February 1, 2023 |
| (2) Questions due from Bidders | June 30, 2023 |
| (3) Response to Questions issued | July 21, 2023 |
| (4) Proposals Due | August 31, 2023 at 5:00 pm HST |
| (5) Selection of Short List | September 22, 2023 |
| (6) Best and Final Offer Due | October 6, 2023 at 5:00 pm HST |
| (7) Selection of Final Award Group | October 20, 2023 |
| (8) Contract Negotiations Start | October 23, 2023 |
| (9) Contract Executed and Filed (estimated) | January 2024 |
| (10) PUC Approval (estimated) | August 2024 |
| (11) Commercial Operations Date | June 30, 2026 |