Grid Services Maui RFP 4 Schedule

Proposed Schedule as of February 1, 2023

Milestone Schedule Dates
(1) RFP issued February 1, 2023
(2) Questions due from Bidders June 30, 2023
(3) Response to Questions issued July 21, 2023
(4) Proposals Due August 31, 2023 at 5:00 pm HST
(5) Selection of Short List September 22, 2023
(6) Best and Final Offer Due October 6, 2023 at 5:00 pm HST
(7) Selection of Final Award Group October 20, 2023
(8) Contract Negotiations Start October 23, 2023
(9) Contract Executed and Filed (estimated) January 2024
(10) PUC Approval (estimated) August 2024
(11) Commercial Operations Date June 30, 2026