Grid Services Maui RFP 4 Schedule

Proposed Schedule as of August 25, 2023

Milestone Schedule Dates
(1) RFP issued February 1, 2023
(2) Questions due from Bidders June 30, 2023
(3) Response to Questions issued July 21, 2023
(4) Proposals Due February 1, 2024 at 5:00 pm HST
(5) Selection of Short List March 1, 2024
(6) Best and Final Offer Due March 15, 2024 at 5:00 pm HST
(7) Selection of Final Award Group March 29, 2024
(8) Contract Negotiations Start April 1, 2024
(9) Contract Executed and Filed (estimated) June 2024
(10) PUC Approval (estimated) February 2025
(11) Commercial Operations Date June 30, 2026