CBRE Tranche 1 RFP Schedule

Proposed Schedule as of August 25, 2021

Milestone Schedule Dates
(1) Draft RFP filed October 9, 2020
(2) Technical Status Conference October 28, 2020
(3) Parties and Participants file Comments by November 13, 2020
(4) Proposed Final RFP filed December 1, 2020
(5) Updated RFP Draft filed Per Order 37592 March 30, 2021
(6) Parties and Participants file Comments by April 14, 2021
(7) Proposed Final RFP filed per Order 37879 August 25, 2021
(8) Final RFP is Issued September 16, 2021
(9) Self-Build Proposal Due Date February 3, 2022 at 2:00 pm HST
(10) IPP and Affiliate Proposal Due Date February 4, 2022 at 2:00 pm HST
(11) Selection of Priority List April 12, 2022
(12) BAFOs due April 20, 2022
(13) Selection of Final Award Group August 3, 2022
(14) Contract Negotiations Start August 10, 2022