Selling Power to the Utility
CBRE Tranche 1 RFP Schedule
Proposed Schedule as of February 23, 2022
| Milestone | Schedule Dates |
|---|---|
| (1) Draft RFP filed | October 9, 2020 |
| (2) Technical Status Conference | October 28, 2020 |
| (3) Parties and Participants file Comments by | November 13, 2020 |
| (4) Proposed Final RFP filed | December 1, 2020 |
| (5) Updated RFP Draft filed Per Order 37592 | March 30, 2021 |
| (6) Parties and Participants file Comments by | April 14, 2021 |
| (7) Proposed Final RFP filed per Order 37879 | August 25, 2021 |
| (8) Proposed Final RFP filed per Order 38217 | February 23, 2022 |
| (9) Final RFP is Issued | April 14, 2022 |
| (10) Self-Build Proposal Due Date | August 16, 2022 at 2:00 pm HST |
| (11) IPP and Affiliate Proposal Due Date | August 17, 2022 at 2:00 pm HST |
| (12) Selection of Priority List | October 25, 2022 |
| (13) BAFOs due | November 1, 2022 |
| (14) Selection of Final Award Group | February 22, 2023 |
| (15) Contract Negotiations Start | March 1, 2023 |