Selling Power to the Utility
CBRE LMI RFP Schedule
Proposed Schedule as of February 23, 2022
| Milestone | Schedule Dates |
|---|---|
| (1) Draft RFP filed | July 9, 2020 |
| (2) Technical Conference | July 29, 2020 |
| (3) Parties and Participants file Comments by | August 12, 2020 |
| (4) Proposed Final RFP filed | September 8, 2020 |
| (5) Updated RFP Draft filed Per Order 37592 | March 30, 2021 |
| (6) Parties and Participants file Comments by | April 14, 2021 |
| (7) Proposed Final RFP filed per Order 37879 | August 25, 2021 |
| (8) Proposed Final RFP filed per Order 38217 | February 23, 2022 |
| (9) Final RFP is Issued | March 17, 2022 |
| (10) IPP and Affiliate Proposal Due Date | May 17, 2022 at 2:00 pm HST |
| (11) Priority List selected | July 26, 2022 |
| (12) BAFOs due | August 2, 2021 |
| (13) Final Award Group selected | November 15, 2022 |
| (14) Contract Negotiations Start | November 22, 2022 |