CBRE LMI RFP Schedule

Proposed Schedule as of August 25, 2021

Milestone Schedule Dates
(1) Draft RFP filed July 9, 2020
(2) Technical Conference July 29, 2020
(3) Parties and Participants file Comments by August 12, 2020
(4) Proposed Final RFP filed September 8, 2020
(5) Updated RFP Draft filed Per Order 37592 March 30, 2021
(6) Parties and Participants file Comments by April 14, 2021
(7) Proposed Final RFP filed per Order 37879 August 25, 2021
(8) Final RFP is Issued September 16, 2021
(9) IPP and Affiliate Proposal Due Date November 16, 2021 at 2:00 pm HST
(10) Priority List selected January 24, 2022
(11) BAFOs due January 31, 2021
(12) Final Award Group selected May 16, 2022
(13) Contract Negotiations Start May 23, 2022