Clean Energy

Net Energy Metering in Hawaii

Updates

June 2015:

Hawaiian Electric Companies release new Transient Overvoltage and expanded Frequency and Voltage Ride-Through requirements to enhance grid safety and reliability.
Qualified Equipment List

February 2015:

Hawaiian Electric Companies continue to move ahead with rooftop PV

January 2015:

Hawaiian Electric Companies propose plan to sustainably increase rooftop solar

If you are thinking about having a photovoltaic (PV) system installed on your roof, you may want to consider visiting our Locational Value Maps (LVM) for Oahu. The LVM is a tool that can give you a rough, preliminary idea about the PV circuit penetration in your area. Please note that the LVM circuit penetration levels change rapidly day by day, and that a completed NEM agreement with any additional required paperwork must first be submitted before your system can be placed in queue for review. Click here to access the Locational Value Maps.

Net Energy Metering (or NEM) is one way to lessen Hawaii’s dependence on imported oil by encouraging the greater use of eligible renewable energy sources like solar (photovoltaic), wind, biomass, or hydroelectric power for electrical generation by residential and commercial customers. Hawaiian Electric Company, Maui Electric Company, and Hawaii Electric Light Company support Net Energy Metering and recognize their roles to help Hawaii transition from fossil fuels to more renewable energy resources. NEM guidelines for Maui and Hawaii Island differ. For information on NEM for Maui, click here. For information on NEM for Hawaii Island, click here.

Forms/Samples/Brochures 

Note:  The NEM documents listed below applies only to Hawaiian Electric. NEM documents for Maui Electric and Hawaii Electric Light differ, so please be sure to visit their respective websites.

Appendix I: Renewable energy generation systems less than 10 kW
Appendix II and Exhibit A: Renewable energy generation systems greater than 10 kW and less than 100  kW 
Amendment to existing NEM Agreement: For existing NEM customers modifying their systems.
Generic Frequency Change Confirmation
180-Day Extension Request Form
NEM Manual: Filling out the Appendix I Agreement
NEM Manual: Filling out the Appendix II Agreement
NEM Manual: Customer-Generator, Property Owners & Signing Authority Information:  Filling out Applicant Information and signatories
Guide to Net Energy Metering brochure: Detailed explanation of the NEM program.
Guide to Going Solar: Understanding the NEM Process: Brief explanation of the NEM application process
Guide to Going Solar: Initial Steps to Take When Considering PV: Helpful tips and considerations prior to installing PV
Guide to Going Solar: Questions to Ask When Selecting a PV Contractor: Sample list of questions to ask when requesting bids from PV Contractors
NEM Bill Summary brochure: Brief explanation on understanding your NEM bill
NEM brochure: Brief explanation of the NEM program
NEM FAQ brochure: NEM FAQ handout
Net Meter Display: Learn how to read a Net Energy Meter 

Mail completed NEM Forms for Oahu installations to: 

Via United States Postal Service:
Hawaiian Electric Company
Attn: Net Energy Metering
PO Box 2750, CP12-SE
Honolulu, Hawaii 96840

Via Private Delivery Services (UPS, FedEx, etc.):
Hawaiian Electric Company
Attn: Net Energy Metering
220 South King St., Suite 1290
Honolulu, Hawaii 96813

No walk-ins, please.

Contact NEM Hotline 

Oahu (Hawaiian Electric Company): (808) 543-4760
Email: nem@hawaiianelectric.com
Maui (Maui Electric Company): (808) 871-8461 ext. 2455
Email: meconem@mauielectric.com
Hawaii (Hawaii Electric Light Company): (808) 969-0358
Email: LVM@hawaiielectriclight.com

Commonly Asked Questions 

  1.  What is net energy metering? 

  2.  What is the value of NEM?

  3.  What types of generators are eligible? 

  4.  Does a solar water heating system qualify for net energy metering?

  5.  How many customers can sign up? 

  6.  Will I need a new meter and, if so, do I need to pay for it? 

  7.  What are the requirements for execution of the NEM agreement? 

  8.  How do I get County building permits closed?

  9.  What happens to my electric bill if I generate more electricity than I use from the utility?

10.  How do I sign up for NEM?

11.  Why are interconnection requirements necessary?

12.  What if I want to add more capacity?

13.  How are requirements established for NEM?

14.  How can I get more information about renewable energy systems that might qualify for NEM?.

15.   Why does my bill not match my inverter(s) output?

16.  How do I read my Net Energy Meter? 

1 .  What is net energy metering?

According to Hawaii state law (Hawaii Revised Statutes (HRS) Section 269-101 - 269-111), all residential and commercial utility customers who own and operate an eligible renewable energy generation system up to a generating capacity of 100 kW and intend to connect to utility grid, must obtain approval to interconnect their system with the utility by executing a NEM agreement.  The executed agreement allows the NEM customer to connect their renewable generator to the utility grid, allowing it to export surplus electricity into the grid, and to receive credits at full retail value which can be used to offset electricity purchases over a 12-month period.  

NEM customers are billed for net energy purchased, which is determined by subtracting the excess energy exported to the utility grid from the total energy supplied by the utility. Here is the formula: 

     Energy Supplied by the Utility (kWh)
 -   Excess Energy exported to the Utility (kWh)
      Net Energy Billed to the Customer (kWh)

2 .  What is the value of NEM?

NEM allows you to offset all or part of your electricity purchases from the utility by energy produced by your eligible renewable generation system.

NEM gives value to the excess electricity you produce with your renewable generation system. Electricity generated by your renewable generator would first supply power for your own needs and any additional power you need would be purchased from the utility. When a NEM customer generates more electricity than what is consumed, excess energy produced can be exported back to the utility at full retail value which can be used to offset electricity purchases over a 12-month period.

This is in contrast to other non-NEM customers with renewable energy generation systems. If they have a power purchase agreement, they are compensated for power exported to the utility grid at a lower wholesale rate. Standard interconnection customers must consume all electricity that is self-generated, and not allow to export surplus energy to the grid nor be compensated. With NEM, you are in effect being given the retail credit for excess power which you generate.

3.  What types of generators are eligible?

Hawaii law specifies that NEM applies to solar, wind, biomass or hydroelectric generation facilities, or a hybrid system of two or more of these technologies, with a capacity up to 100 kW. (For more information about these technologies, visit the website of the State of Hawaii, Department of Business, Economic Development and Tourism, Strategic Industries Division, Energy Branch).

The Hawaii Public Utilities Commission (PUC), by rule or order, can change the maximum allowable capacity.

4.  Does a solar water heating system qualify for net energy metering?

No. NEM applies only to systems that generate electricity. Solar electric systems, known as photovoltaics (PV), use solar cells to convert the sun’s light into electricity. By contrast, solar water-heating systems use heat from the sun directly to heat water for your use. Since solar water-heating systems do not produce electricity, they cannot feed into the grid and do not qualify for NEM.

5 .  How many customers can sign up?

To ensure continued reliable service for all of our customers on a distribution circuit, a technical review is required for all systems over 10 kW in capacity, and for smaller systems when the circuit daytime minimum load (DML) is over 75%.  This is not a limit on solar or other DG. This threshold serves as a trigger point for determining whether additional study may be needed to evaluate the impact of additional DG on the circuit. The purpose is to determine if any steps must be taken to ensure service remains reliable for all customers on that circuit when adding more DG.  This is consistent with the standards used by California electric utilities. 

To find out the circuit penetration level for your project, please visit the Locational Value Map (LVM) for Oahu.

6.  Will I need a new meter and, if so, do I need to pay for it?

New and existing NEM systems will require a new bi-directional meter capable of measuring the energy supplied by your utility and the excess electricity from your renewable energy generation system exported to the grid. Hawaiian Electric will provide the meter at no cost to you when the NEM agreement is executed.

If you are planning to install a qualified renewable energy generation system and have an existing electric meter with a digital display, please call Hawaiian Electric at 543-4760 to confirm if your meter is compatible to ensure proper credit can be given. Your existing meter may have to be replaced before your system can be energized. If you have an existing mechanical meter, it will be replaced when the NEM agreement is executed.

All meters must be accessible by Hawaiian Electric personnel for emergencies, meter reading, inspection, testing, and maintenance in accordance with the tariff and Hawaiian Electric's Electric Service Installation Manual.  For billing purposes the net meter displays more data than your current meter and needs to be manually read.  Please note that upon execution (signing) of a NEM agreement, you agree to allow Hawaiian Electric personnel entry to your property during normal business hours to read and perform maintenance on the meter. If the customer plans to make modifications or additions which would render the metering facilities inaccessible, the customer must consult with Hawaiian Electric before making such modifications or additions, and make arrangements satisfactory to the utility for continued access by its workers.

See meter handout to learn how to read a Net Energy meter, or See video on how to read a Net Energy Meter.

7.  What are the requirements for execution of the NEM agreement?

For qualified renewable energy generation systems less than 10 kW:

  1. Submit a complete Appendix I agreement, signed by both the property owner and the licensed electrical contractor who completed the work. If applicable, the authorized representative of the owner-operator of the system must also sign. See the NEM Manual: Filling out the Appendix I, for more details.
  2. Submit a single-line drawing accurately depicting interconnection of the generating facility with the utility. See our sample single-line drawing.
  3. A lockable utility disconnect must be installed within close proximity of the meter or the electrical room. Approval is needed if the utility disconnect cannot be placed near the meter. This also requires installation of appropriate signage.
  4. The City & County of Honolulu must inspect the renewable energy generation system and close the permits for the project. Please call or email us once your permit closes.
  5. Where required, a signed “Addendum No. 1” must be submitted, and your system must comply with the technical requirements marked therein.
  6. As of February 9, 2015, all inverters used in new DG systems must meet both transient overvoltage and ride-through specifications. Screenshots of the completed ride-through reprogramming must be sent to us before the agreement can be executed.

For qualified distributed generation systems greater than 10 kW but no more than 100 kW:

  1. Download Rule 18 – Net Energy Metering and complete Appendix II and Exhibit A. The property owner must sign the agreement.
  2. Systems >10kW to <=30kW:
    • Submit a single-line drawing accurately depicting the interconnection of the generating facility with the utility. Include plot diagrams showing locations for panels, inverters, disconnects, and the meter in relation to the street (elevation may be required if components are on different levels). If necessary, include a relay list and trip scheme.
  3. Systems >30kW to <=100kW:
    • Submit a three-line drawing with a licensed professional electrical engineer’s stamp, accurately depicting the interconnection of the generating facility with the utility (including a relay list and trip scheme, if necessary). Include plot diagrams showing locations for panels, inverters, disconnects, and the meter in relation to the street (elevation may be required if components are on different levels). If necessary, include a relay list and trip scheme.
  4. Submit a certificate of insurance, as required in section 6 of the NEM agreement. See insurance requirements below.
  5. A lockable utility disconnect must be installed within close proximity of the meter or the electrical room. Hawaiian Electric must approve proper signage if the utility disconnect cannot be placed beside the meter.
  6. The City & County of Honolulu must inspect the DG system and close the permits for the project. Please call or email us once your permit closes.
  7. Where required, a signed “Addendum No. 1” must be submitted, and your system must comply with the technical requirements marked therein.
  8. As of February 9, 2015, all inverters used in new DG systems must meet both transient overvoltage and ride-through specifications. Screenshots of the completed ride-through reprogramming must be sent to us before the agreement can be executed.
 

8 .  How do I get County building permits closed?

Call the contractor who installed your renewable energy generation system and have the contractor schedule an appointment with the electrical and building inspectors. The licensed electrician who completed the work needs to be present during the inspection. Closure of the building permit signifies that your system has been inspected and found to be designed and installed in conformance with applicable codes for safe operation. Final inspection and approval by both the building and electrical inspectors are required and are a vital part of executing a NEM agreement.

In accordance with Rule 18 of the tariffs, the utility will not execute a NEM agreement without approvals and closure of applicable permits. Please check with your County permit office to determine the status of your permits. On Oahu, you can review the status of your permit by accessing the Honolulu Department of Planning and Permitting website.

Enter your address or permit number on the form and click “GO” to search the permit database for the status of all permits on this site. Please call your utility to inform them when your inspection has been completed and the permit has been closed

.

9 .  What happens to my electric bill if I generate more electricity than I use from the utility?

Billing is on a monthly basis and you are responsible for a minimum charge even if you export more electricity than you take from the utility. The minimum charge covers some of the fixed costs of maintaining your electric account.

The NEM agreement allows the customer to carry over unused credits (excess net generation expressed as a monetary value) to future bills within a 12 month period, starting from when the agreement is executed. Unused credits left at the end of each 12- month reconciliation period may not be carried over to the next 12-month period.

10.  How do I sign up for NEM?

In general, for systems up to 10 kW, you will need to enter into a simple NEM agreement with the utility which must be submitted and approved before your renewable energy generation system has been installed. Your contractor or electrician must obtain a building permit and have a licensed electrical contractor sign and certify your renewable energy generation system meets the necessary safety standards. Click here to download our Understanding the Net Energy Metering Process brochure for additional information. NEM application processes for Hawaii Electric Light Company and  Maui Electric Company may differ; please check their websites for details.

The building and electrical inspectors from the County office on your island will conduct an inspection to verify your renewable energy generation system meets required safety standards and they will proceed to close the building permit accordingly. See question 8 above for more information.

For all proposed NEM systems, the utility will perform an interconnection review. Unless more detailed study is needed, this review will be at no charge. It is highly recommended that you contact your utility early in your planning process to determine if they can accommodate the additional generation from your renewable energy generation system. Any additional costs for facilities needed to complete the interconnection review will be the responsibility of the customer.

Also for systems over 10 kW but not more than 100 kW, you must enter into a more detailed customer agreement (see question 8 under download Rule 18 – Net Energy Metering Appendix II) that specifies the technical requirements necessary to ensure your renewable energy generation system can safely be connected to the utility grid. You will also need to provide proof of a commercial general liability insurance policy. The agreement must be signed by the licensed electrical contractor who installed your renewable energy generation system to certify that your renewable energy generation system meets the necessary safety standards and that an electrical permit was issued.

For photovoltaic energy generation systems up to 100 kW, the interconnection process is more streamlined especially if your system has an approved DC-AC inverter and PV Modules.

Here is a list of eligible inverters.

Here is a list of eligible PV modules.

Here is a list of approved equipment that meets TOV specifications.

Please mail the NEM agreement to:

Via United States Postal Service:
Hawaiian Electric Company
Attn: Net Energy Metering
PO Box 2750, CP12-SR
Honolulu, Hawaii 96840
Via Private Delivery Services (UPS, FedEx, etc.):
Hawaiian Electric Company
Attn: Net Energy Metering
220 South King St., Suite 1290
Honolulu, Hawaii 96813
 

11 .  Why are interconnection requirements necessary?

If your renewable energy generation system mistakenly back-feeds power into an electric line that utility crews think is de-energized, the crews can be seriously injured or even killed. The interconnection study also helps assure the utility that you and other customers continue to receive reliable service and good power quality, avoiding potentially disruptive swings in voltage levels that could damage your equipment and that of the utilities.

Whether you are installing a new renewable energy generation system or considering NEM for an existing renewable energy generation system, compliance with all safety and other codes are required.

12 .  What if I want to add more capacity?

If you are an existing NEM customer (with an executed NEM agreement) and want to increase your generating capacity, you must complete the Amendment to existing NEM Agreement and mail it back to Hawaiian Electric within 30 days.  The addition to your existing system will undergo the technical review process.  

13 .  How are requirements established for NEM?

The 2005 Legislature, by Act 104, gave the Hawaii Public Utilities Commission authority to set requirements and limits as well as safety, performance, and reliability standards for NEM by order, tariff, or rule.

  14.  How can I get more information about renewable energy systems that might qualify for NEM?

Please call the utility or check their websites (by clicking on the company links below) on your island for more information:

 Island  Company  Phone  Email
 Oahu Hawaiian Electric Company (808) 543-4760  nem@hawaiianelectric.com
 Maui Maui Electric Company (808) 871-8461 ext. 2455  meconem@mauielectric.com
 Hawaii Hawaii Electric Light Company (808) 969-0358  LVM@hawaiielectriclight.com

 
For information on how to obtain a building permit on Oahu (if needed), call: City & County of Honolulu 768-8239

Here are printable NEM brochures (in PDF format).
           NEM brochure 
           NEM FAQ brochure        

15.  Why does my bill not match my inverter(s) output?

Net Energy Metering is intended to offset part or all of customer's electric consumption from the Utility.  During sunny days with low household consumption a customer's PV system may generate more electricity than used by the customer.  Under these conditions the excess will flow back through the Utility meter to the grid.  On other days a customer's PV system may not generate enough electricity to completely power the customer's load.  In this case some electricity will flow from the grid through the Utility meter to supply the remaining power for the customer.  Only the electricity flowing to and from the grid is measured by the Utility meter.  The Utility meter will not measure the electricity generated by the customer's PV system to the customer's load.  The Utility meter will only measure the excess electricity going back to the grid or the extra power supplied from the grid.  Therefore, the energy measured by the Utility meter will not match the energy measured by the PV inverters. See PV system diagram below..

16.  How do I read my Net Energy Meter?

Click on the video below to learn how to read a Net Energy Meter.